Optimization of implementation of strategic priorities of the organization by means of the network planning and management model

Development of a network planning model for solving the strategic priorities of the organization. Estimation of terms of execution of tasks, optimization of performers. Determination of the tension coefficient for the implementation of the priority.

Рубрика Менеджмент и трудовые отношения
Вид статья
Язык английский
Дата добавления 27.01.2021
Размер файла 364,7 K

Отправить свою хорошую работу в базу знаний просто. Используйте форму, расположенную ниже

Студенты, аспиранты, молодые ученые, использующие базу знаний в своей учебе и работе, будут вам очень благодарны.

Размещено на http://www.Allbest.Ru/

Narxoz university the Republic of Kazakhstan, Almaty

Optimization of implementation of strategic priorities of the organization by means of the network planning and management model

Shoranova A.E., Doctoral student of DBA

Республика Казахстан, г. Алматы

Summary

Development of any business is impossible without strategic planning of activities and determination of strategic priorities for the development of an organization. Moreover, the process of determining strategic priorities is not so complicated compared to the process of their implementation. The implementation of strategic priorities requires a well-developed plan with a hierarchy of decisions and stages for the implementation of the plan. At the same time, important decisions on the implementation and implementation of strategic priorities are assigned to managers at various levels.

The paper shows the option of applying the network planning model to the issue of the implementation of strategic priorities to the organization. Using the model made it possible to estimate the maximum and minimum possible deadlines for the execution of tasks, the total time reserves, optimize the number of executors, determine the critical path and tension coefficient for the implementation of the priority under consideration when the layout of cases is formed: a certain number of executors for each task, the optimal deadline for implementation of tasks.

Keywords: network planning, strategic priorities, critical path, tension coefficient, performers optimization.

Аннотация

Оптимизация реализации стратегических приоритетов организации посредством модели сетевого планирования и управления

Шоранова А.Е., докторант DBA, АО «Университет Нархоз»

Развитие любого бизнеса невозможно без стратегического планирования деятельности и определения стратегических приоритетов развития организации. Более того, сам процесс определения стратегических приоритетов еще не настолько сложен по сравнению с процессом их реализации. Реализация стратегических приоритетов требует четко разработанного плана с составлением иерархии решений и этапов осуществления плана. При этом важные решения по осуществлению и претворению стратегических приоритетов в жизнь возлагаются на менеджеров различных уровней.

В статье показан вариант применения модели сетевого планирования к вопросу реализации стратегических приоритетов к организации. Использование модели позволило оценить максимально и минимально возможные сроки исполнения задач, полные резервы времени, оптимизировать число исполнителей, определить критический путь и коэффициент напряженности по реализации рассматриваемого приоритета при сформированной раскладке дел: определенном количестве исполнителей по каждой задаче, оптимальном сроке выполнения, установленном порядке выполнения задач.

Ключевые слова: сетевое планирование, стратегические приоритеты, критический путь, коэффициент напряженности, оптимизация исполнителей.

Formulation of the problem

Important tasks in the process of implementing strategic priorities are the identification of resources, stages and timelines for the implementation of relevant activities. The need for resources depends on the specifics of the implementation of strategic priority. In this case, a budget is drawn up in which all the necessary expenses for the implementation of each priority separately are recorded.

A significant role in the implementation of the strategic priorities of the organization's development is assigned to human resources. It is important for the manager to clearly know the abilities of each employee who is potentially capable of fulfilling the tasks of implementing the respective strategic priority. It is also necessary to clearly define the order of actions and stages of implementation of tasks. In addition, the timing of the implementation of various tasks on the implementation of development priorities is of great importance. As a rule, the deadlines for implementation will depend on both human resources (quality and timeliness of execution of orders), and the schedule of execution determined by the manager at the appropriate level.

Analysis of recent research and publications

In the contemporary practice of many large companies, network management models are used that imply a departure from the top-down hierarchical control system [1]. The peculiarity of the network model lies in the horizontal management structure, i.e., communication is actions (operations). At the same time, the link suggests that some operations cannot be carried out until the other tasks preceding them are performed.

Using of network models of planning and management allows you to optimize the process of implementing strategic priorities. Since the achievement of each strategic priority is possible only with the implementation of certain tasks that are carried out in a strictly defined sequence.

In management tasks, methods of generating columns, the use of the Lagrange function [3], linear programming, various regression models [4], the Hungarian assignment task method [5], the heuristic algorithm [6] and [7] are often used. Various variants of mathematical models are also widely used: the Pareto method and the hierarchical method [8], the technique for determining bottlenecks [9], multi-criteria linear programming [10], various optimization methods [11].

The effectiveness of the use of network planning models is considered in the works of A.E. Polichka, E.V. Simonova in mathematical modeling of building disciplines [12], E.V. Bucenko, A.F. Shorikov in optimizing business planning processes [13].

Unsolved part of the problem

In general, network planning uses a graphical display of the work plan in their logical sequence and interconnection and allows you to subsequently optimize the current management by adjusting the original plan [14]. The use of network modeling allows you to analyze all the work and make improvements to the structure of the model prior to its implementation [15].

All these features of the network model, in our opinion, allow it to be applied to the process of implementing strategic priorities in an organization.

The purpose of the paper is to study the possibility of using network planning in the tasks of determining the strategic priorities of the organization.

Methods

To assess the plan for the implementation of the strategic priority of the organization, we apply the network planning model. The network model is an economic-mathematical model, reflecting a set of operations related to the implementation of a project, in their logical and technological sequence and communication. The analysis of the network model presented in graphical or tabular form allows, first, to more clearly identify the interrelationships of the project implementation stages and, secondly, to determine the most optimal order of implementation of these stages in order, for example, to reduce the implementation time for the whole complex of works. Thus, network modeling methods can be attributed to the methods of making optimal decisions.

In our case, the project is the implementation of strategic priority. At the same time, the duration of the work is set by three estimates - the minimum, maximum and optimal. The minimum estimate tmin (i, j) characterizes the duration of the work under the most favorable circumstances, and the maximum tmax (i, j) - under the most adverse conditions.

Duration of work in this case is considered as a random variable, which as a result of the implementation can take any value in a given interval. The expected value of tex(i, j) is estimated by the formula:

(1)

m - optimal task execution time [16].,

To characterize the degree of variation of possible values around the expected level, the variance is used, which is estimated as follows:

(2)

To determine the time reserves for network events, the earliest tp and the latest tp deadlines for event completion are calculated. Any event cannot occur before all the events preceding it are completed and all previous works are not performed. Therefore, the early (or expected) time tp(i) of accomplishing the i-th event is determined by the duration of the maximum path preceding this event:

, (3)

Lni - any path preceding the i-th event, that is, the path from the source to the i-th event of the network.

The delay in the occurrence of event i in relation to its early date will not affect the period of accomplishment of the final event (and, therefore, the period of performance of the complex of works) until the sum of the period of accomplishment of this event and the length (length) of the maximum of the following exceed the lengths of the critical path. Therefore, the late (or deadline) term tn(i) of accomplishing the i-th event is:

(4)

Lci - any path following the i-th event, i.e. path from the i-th to the final network event.

The time reserve R(i) of the i-th event is defined as the difference between the late and early dates of its accomplishment:

(5)

To determine the maximum possible implementation time for the whole work package with a 95% reliability, we will use the following formula:

, (6)

Z - normative deviation of a random variable,

SKP - standard deviation, calculated as the square root of the variance of the duration of the critical path.

The complexity of the network schedule is estimated by the complexity factor, which is determined by the formula:

, (7)

nw - number of works, units; nev - number of events, units.

The coefficient of intensity K of work Pя is the ratio of the duration of non-coincident (prisoners between the same events) segments of the path, one of which is the path of maximum duration passing through this work, and the other is the critical path:

, (8)

t(Lmax) - the duration of the maximum path through Py, from the beginning to the end of the network schedule;

tcr - duration (length) of the critical path; tlcr - the length of the segment of the considered maximum path coinciding with the critical path.

Research results

Let us consider an example of using network planning for the implementation of the strategic priority “Increasing the company's market share”. As it was said, for the implementation of strategic priority it is necessary to determine the complex of operations (works) and the timing of their implementation (table l).

Table 1

Complex tasks within the framework of the implementation of strategic priority

Task name

Designation

Job Code

Deadline, days

Number of performers, people

min

max

°p-tim

Evaluation of the company's position in the market

A

(0,1)

10

14

12

4

Environmental analysis

B

(1,2)

14

20

18

5

Analysis of internal factors

C

(1,3)

12

18

16

3

Competition evaluation

D

(1,4)

20

28

24

4

Market risk assessment

E

(2,5)

5

7

6

2

Internal risk assessment

F

(3,5)

8

12

10

3

Analysis of potential customers

G

(4,6)

12

16

14

4

Definition of marketing strategies

H

(5,6)

20

28

24

5

Determination of the optimal selling price of products

I

(6,7)

5

10

7

3

Budgeting

J

(6,8)

3

6

5

3

Develop a financial plan

K

(8,9)

7

14

10

5

Calculation of financial indicators

L

(7,9)

3

5

4

3

Calculate the expected value and indicators of variance. The results are presented in table 2. network planning strategic priority

Using the data obtained, it is possible to find the main characteristics of the network model by a tabular method, the critical path and its duration.

The most important indicator of the network schedule is the time reserves. The time reserves of each path show the extent to which the duration of a given path can be increased without prejudice to the onset of the final event. Since each non-critical network path has its full time reserve, each event on this way has its own time reserve.

Table 2

The results of the evaluation of the expected duration of time and variance

Task (i,j)

tmin(i,j)

tmax(i,j)

m(i,j)

Expected duration tex(i,j)

Dispersion S2(i,j)

0,1

10

14

12

12

0.44

1,2

14

20

18

17,67

1

1,3

12

18

16

15,67

1

1,4

20

28

24

24

1,78

2,5

5

7

6

6

0,11

3,5

8

12

10

10

0,44

4,6

12

16

14

14

0,44

5,6

20

28

24

24

1,78

6,7

5

10

7

7,17

0,69

6,8

3

6

5

4,83

0,25

8,9

7

14

10

10,17

1,36

7,9

3

5

4

4

0,11

Critical events of reserves of time do not have, since any delay in the accomplishment of an event lying on a critical path will cause the same delay in the accomplishment of the terminating event. Thus, by determining the early date of the onset of the terminating network event, one can determine the length of the critical path.

The results of the deadlines and time reserve are presented in table 3.

Table 3

Calculate the tjming and time reserve

Event

number

Deadlines for the event: early tp(i)

Deadlines for the event: late tn(i)

Time reserve, R(i)

0

1,7763568394003E-15

1,7763568394003E-15

1

12

12

1,7763568394003E-15

2

29,67

31,67

2

3

27,67

27,67

0

4

36

47,67

11,67

5

37,67

37,67

0

6

61,67

61,67

0

7

68,84

72,67

3,83

8

66,5

66,5

0

9

76,67

76,67

0

In determining the early dates for completing the tp(i) events, we move along the network graph from left to right and use formula (3).

The length of the critical path is equal to the early completion date of the event 9: tkp = tp(9) = 76,67

When determining the late dates for accomplishing the events tn(i), we move along the network in the opposite direction, that is, from right to left and use formula (4).

The total reserve of the path shows how much the total duration of all the work belonging to the given path can be increased, provided that the duration of the whole complex of works does not change. It is formed when the previous work will end at its earliest date.

Rf(o,d = 12-12-0 = 1,7763568394003E-15

Rf(4,6) = 61,67-14-36 = 11,67

Rf (1,2) = 31,67-17,67-12 = 2

Rf(5,6) = 61,67-24-37,67 = 0

Rf(i,3) = 27,67-15,67-12 = 0

Rf(6,7) = 72,67-7,17-61,67 = 3,83

Rf(1,4) = 47,67-24-12 = 11,67

Rf(6,8) = 66,5-4,83-61,67 = 0

Rf(2,5) = 37,67-6-29,67 = 2

Rf(7,9) = 76,67-4-68,84 = 3,83

Rf(3,5) = 37,67-10-27,67 = 0

Rf(8,9) = 76,67-10,17-66,5 = 0

Определим свободный резерв времени:

Rf(0,1) = 12-12-0 = 0

Rf(4,6) = 61,67-14-36 = 11,67

Rf(1,2) = 29,67-17,67-12 = 0

Rf(5,6) = 61,67-24-37,67 = 0

Rf(1,3) = 27,67-15,67-12 = 0

Rf(6,7) = 68,84-7,17-61,67 = 0

Rf(1,4) = 36-24-12 = 0

Rf(6,8) = 66,5-4,83-61,67 = 0

Rf(2,5) = 37,67-6-29,67 = 2

Rf(7,9) = 76,67-4-68,84 = 3,83

Rf(3,5) = 37,67-10-27,67 = 0

Rf(8,9) = 76,67-10,17-66,5 = 0

Let us analyze the network model in terms of the implementation of tasks on the implementation of strategic priority (Table 4).

Table 4

Analysis of the network model by date

Task

Number of

Duration

Early dates:

Early deadline:

Late deadline:

Minimum

(i,j)

previous works

hi

start

ending

ending

cut

(0,1)

0

10

0

10

10

10

(1,2)

1

14

10

24

25

24

(1,3)

1

12

10

22

22

22

(1,4)

1

20

10

30

38

30

(2,5)

1

5

24

29

30

29

(3,5)

1

8

22

30

30

30

(4,6)

1

12

30

42

50

42

(5,6)

2

20

30

50

50

49

(6,7)

2

5

50

55

57

47

(6,8)

2

3

50

53

53

45

(7,9)

1

3

55

58

60

58

(8,9)

1

7

53

60

60

60

We choose the minimum value for all work ending in 9, which was 58. Therefore, the minimum time for completion of all tasks for the implementation of strategic priority will be 58 days.

We estimate the coefficients of complexity and intensity. Network models that have a complexity factor from 1.0 to 1.5 are simple, from 1.51 to 2.0 - medium complexity, more than 2.1 - complex. In our case, the complexity factor was:

Kd = 12 / 10 = 1,2

Since Kd <1.5, the network model is simple.

The coefficient of intensity K of work Py can vary from 0 (for work in which the maximum length of the paths that do not coincide with the critical path consists of fictitious works of zero duration) to 1 (for the work of the critical path). The closer to 1 coefficient of tension K of work Py, the more difficult it is to perform this work in a timely manner. The closer to the work of Py to zero, the greater the relative reserve has the maximum path that passes through this work. The results of the calculation of the coefficient of tension are presented in table 5.

Table 5

The coefficient of intensity

Task

Way

Maximum way, t(Lmax)

Matching works

t1cr

Calculation

K

(0,1)

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(1,2)

(0,1)(1,2)

(2,5)(5,6)

(6,8)(8,9)

74,67

(0,1)(5,6)

(6,8)(8,9)

51

(74,67-51)/(76,67-51)

0,922

(1,3)

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(1,4)

(0,1)(1,4) (4,6)(6,8) (8,9)

65

(0,1)(6,8) (8,9)

27

(65-27)/(76,67-27)

0,765

(2,5)

(0,1)(1,2)

(2,5)(5,6)

(6,8)(8,9)

74,67

(0,1)(5,6)

(6,8)(8,9)

51

(74,67-51)/(76,67-51)

0,922

(3,5)

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(4,6)

(0,1)(1,4) (4,6)(6,8) (8,9)

65

(0,1)(6,8) (8,9)

27

(65-27)/(76,67-27)

0,765

(5,6)

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(6,7)

(0,1)(1,3)

(3,5)(5,6)

(6,7)(7,9)

72,84

(0,1)(1,3)

(3,5)(5,6)

61,67

(72,84-61,67) / (76,67-61,67)

0,745

(6,8)

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(7,9)

(0,1)(1,3)

(3,5)(5,6)

(6,7)(7,9)

72,84

(0,1)(1,3)

(3,5)(5,6)

61,67

(72,84-61,67)/(76,67-61,67)

0,745

(8,9)

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

(0,1)(1,3)

(3,5)(5,6)

(6,8)(8,9)

76,67

The calculated stress coefficients allow to further classify work by zones. Depending on the magnitude of the intensity factor K, there are three zones: critical (K > 0,8); subcritical (0,6 <K <0,8) and backup (K < 0,6).

The closer the tension coefficient to unity, the more difficult it is to perform this task in a timely manner; the closer to zero, the greater the relative reserve is the maximum path through this task.

To determine the maximum possible execution time of the whole complex of tasks, we find the value of the argument Z, which corresponds to a given probability of 95% (the value of the F (Z) column is 0,95 * 100% in the table corresponds to Z = 1,96):

T = 76,67+1,96*2 = 80,59

Consequently, the maximum completion time of the whole complex of works at a given 95% probability level is only 81 days.

Figure 1 - Network implementation schedule of strategic priority

Conclusion

The optimization of the deadlines due to the redistribution of resources is based on the fact that tasks that are not on the critical path have time reserves. For the transfer of resources, for example, people, tasks with a tension ratio in the range from 0 to 0,55 are used, which determines the belonging of the task to the reserve zone. Figure 1 shows the network schedule for accomplishing priority tasks and highlights the critical path, the duration of which was 76,67 days.

The figure shows the critical path (0,1) (1,3) (3,5) (5,6) (6,8) (8,9), which ensures the execution of tasks in 77 days. However, the manager should carefully consider the possibility of its implementation without performing other tasks.

The tension coefficients show that all the designated tasks for the implementation of priority fall into the subcritical or critical zone (tasks (1,2) and (2,5)). This means that there is no reserve both in terms of accomplishment of the tasks set and in the number of performers. It is even possible that for tasks falling into the critical zone, additional labor resources will be required. The duration of the minimum journey was 58 days. However, at the set intensity with a probability of 95%, the implementation of the strategic priority will be carried out within 81 days.

Thus, the application of the network planning and management method allows the following:

1) check the feasibility of planned tasks (works) and their structure;

2) identification of unnecessary tasks, for example, not mandatory due to changes in technology;

3) determining the possibility of parallel tasks;

4) the determination of the appropriateness of the level of detail obtained for the tasks, and, if necessary, the dismemberment of certain works in order to increase parallelism.

References / Список использованной литературы

1. A.Koptelov Setevyye modeli upravleniya - vremya prishlo? // Business Excellence, 2012. - №5. - С. 52-55

2. A.Ye. Shadrin Setevaya model' organizatsii

3. Kroon L, Salomon M, van Wassenhove L. Exact and approximation algorithms for the tactical fixed interval scheduling problem // Operations Research, 1997. - №45:6. - рр. 24-38.

4. H.A. Eiselta, Vladimir Marianov Employee positioning and workload allocation// Computers & Operations Research, Elsevier, 2008. - №35. - рр. 513-524

5. Praveena Akki and Poonguzhali.E Resource Allocation and storage using Hungarian method in Mobile Cloud computing//IJARSCCE volume 3, Issue 8, Aug 2013.

6. Jameer. G. Kotwal et al, // International Journal of Computer Science and Information Technologies, 2015. - Vol. 6 (4). - рр. 3736-3741

7. He, J., Huang, Y., & Chang, D. Simulation- based heuristic method for container supply chain network optimization//Advanced Engineering Informatics, 2015. - №29(3), 339-354.

8. Vladimir I. Voropaev, Yan D. Gelrud project management mathematical models for the customer // PM World Journal, 2013. - Vol.2, issue 3

9. Barkalov S.A., Kolpachev V.N., Glagol'yev A.V., Likhotin YU.P. Dvoynaya setevaya model' optimizatsii kalendarnogo grafika // Prikladnyye zadachi modelirovaniya i optimizatsii. Mezhvuzovskiy sbornik nauchnykh trudov. - Voronezh: ВГТУ, 2002. С. 141-148.

10. Medvedev A.V. Kontseptsiya optimi- zatsionno-imitatsionnogo biznesplanirovaniya // Mezhdunarodnyy zhurnal prikladnykh i fundamen- tal'nykh issledovaniy. 2014. №1. С. 198-201.

11. Mutyash I.V., Chudosay A.V. Vnedreniye sis- temy biznes-planirovaniya kak instrumenta upravleniya predpriyatiyem pishchevoy promyshlennosti v usloviyakh finansovoy neustoychivosti: teoretich- eskiye aspekty i prakticheskiye resheniya (na primere OAO «Bamaul'skiy drozhzhevoy zavod») // Izvestiya Altayskogo gosudarstvennogo universiteta. 2015. Т. 1, №2 (86). С. 117-122.

12. A.Ye. Polichka, Ye.V. Simonova Problema razrabotki setevoy matematicheskoy modeli uchebnoy distsipliny magistratury// «Uchenyye zametki TOGU», 2016. - Том 7, №4. - С.509-512

13. Ye.V.Butsenko, A.F. Shorikov Realizatsiya setevogo ekonomiko-matematicheskogo modelirovaniya dlya protsessa biznes-planirovaniya // Vestnik UrFU. Seriya ekonomika i upravleniye, 2015. - Том №6. - С.935-953

14. K.M. Karenov Teoreticheskiye i metodicheskiye osnovy optimizatsii setevykh modeley po vremeni // Vestnik KarGU: Karaganda, 2012

15. A.A.Kopaneva, A.V. Ovsyannikova, I.F.Avdeyev. Matematicheskiye metody v ekonomike. Uchebno-metodicheskoye posobiye dlya studentov ekonomicheskikh spetsial'nostey.- M.: MGUTU, 2009

16. Ye.V. Freydina Issledovaniye sistem upravleniya: ucheb. posobiye / Ye.V. Freydina; pod red. YU.V. Guseva. - 5-ye izd., ster. - M.: Omega-L, 2013. - 367 с.

Размещено на allbest.ru

...

Подобные документы

  • The impact of management and leadership styles on strategic decisions. Creating a leadership strategy that supports organizational direction. Appropriate methods to review current leadership requirements. Plan for the development of future situations.

    курсовая работа [36,2 K], добавлен 20.05.2015

  • The audience understand the necessity of activity planning and the benefits acquired through budgeting. The role of the economic planning department. The main characteristics of the existing system of planning. The master budget, the budgeting process.

    презентация [1,3 M], добавлен 12.01.2012

  • Definition of management. The aim of all managers. Their levels: executives, mid-managers and supervisors. The content and value of basic components of management: planning, organizing, coordinating, staffing, directing, controlling and evaluating.

    презентация [414,2 K], добавлен 16.12.2014

  • Types of the software for project management. The reasonability for usage of outsourcing in the implementation of information systems. The efficiency of outsourcing during the process of creating basic project plan of information system implementation.

    реферат [566,4 K], добавлен 14.02.2016

  • Analysis of the peculiarities of the mobile applications market. The specifics of the process of mobile application development. Systematization of the main project management methodologies. Decision of the problems of use of the classical methodologies.

    контрольная работа [1,4 M], добавлен 14.02.2016

  • The essence, structure, оbjectives and functions of business plan. The process’s essence of the bank’s business plan realization. Sequential decision and early implementation stages of projects. Widely spread mistakes and ways for their improvement.

    курсовая работа [67,0 K], добавлен 18.12.2011

  • The primary goals and principles of asset management companies. The return of bank loans. Funds that are used as a working capital. Management perfection by material resources. Planning of purchases of necessary materials. Uses of modern warehouses.

    реферат [14,4 K], добавлен 13.05.2013

  • Organizational structure: types of organizational structures (line organizations, line-and-Stuff organizations, committee and matrix organization). Matrix organization for a small and large business: An outline, advantages, disadvantages, conclusion.

    реферат [844,8 K], добавлен 20.03.2011

  • Investigation of the subjective approach in optimization of real business process. Software development of subject-oriented business process management systems, their modeling and perfection. Implementing subject approach, analysis of practical results.

    контрольная работа [18,6 K], добавлен 14.02.2016

  • Logistics as a part of the supply chain process and storage of goods, services. Logistics software from enterprise resource planning. Physical distribution of transportation management systems. Real-time system with leading-edge proprietary technology.

    контрольная работа [15,1 K], добавлен 18.07.2009

  • Relevance of electronic document flow implementation. Description of selected companies. Pattern of ownership. Sectorial branch. Company size. Resources used. Current document flow. Major advantage of the information system implementation in the work.

    курсовая работа [128,1 K], добавлен 14.02.2016

  • Searching for investor and interaction with him. Various problems in the project organization and their solutions: design, page-proof, programming, the choice of the performers. Features of the project and the results of its creation, monetization.

    реферат [22,0 K], добавлен 14.02.2016

  • Organizational structure of the company. Analysis of the external and internal environment. Assessment of the company's competitive strength. Company strategy proposal. Structure of implementation and creation of organizational structure of management.

    дипломная работа [2,7 M], добавлен 19.01.2023

  • Company’s representative of small business. Development a project management system in the small business, considering its specifics and promoting its development. Specifics of project management. Problems and structure of the enterprises of business.

    реферат [120,6 K], добавлен 14.02.2016

  • Leaders are those who can make others perform tasks without being coerced through force or formal authority. Conflict Management Styles. Teambuilding is essential in the workplace and highly desirable skills to possess when seeking a new job, promotion.

    реферат [23,7 K], добавлен 04.01.2016

  • Milestones and direction of historical development in Germany, its current status and value in the world. The main rules and principles of business negotiations. Etiquette in management of German companies. The approaches to the formation of management.

    презентация [7,8 M], добавлен 26.05.2015

  • Характеристика особенностей одного из наиболее распространенных методов управления производством и дистрибуции - стандарта MRPII (Manufacturing Resource Planning). Концепция ERP. Функции прогнозирования спроса, управления проектами, затратами, кадрами.

    реферат [17,9 K], добавлен 15.04.2011

  • Стратегия внедрения ERP-систем (от Enterprise Resources Planning - управление ресурсами предприятия) на российских предприятиях как средства оптимизации и поддержки бизнеса. Специфика российского сервиса и аренды: функциональные требования к ERP-решению.

    реферат [204,5 K], добавлен 29.05.2009

  • The concept, essence, characteristics, principles of organization, types and features of the formation of groups of skilled workers. The general description of ten restrictions which disturb to disclosing of potential of group staff and its productivity.

    реферат [29,7 K], добавлен 26.07.2010

  • Impact of globalization on the way organizations conduct their businesses overseas, in the light of increased outsourcing. The strategies adopted by General Electric. Offshore Outsourcing Business Models. Factors for affect the success of the outsourcing.

    реферат [32,3 K], добавлен 13.10.2011

Работы в архивах красиво оформлены согласно требованиям ВУЗов и содержат рисунки, диаграммы, формулы и т.д.
PPT, PPTX и PDF-файлы представлены только в архивах.
Рекомендуем скачать работу.